4 Common Methods for Risk Analysis:
- Expected Value
- Decision Trees
- Payoff Tables
- Simulation
The 5 Principles Underlying the Definition of Risk:
- There are many risk in a project. All uncertainty in a project plan that you can control or track is considered a risk. The risks that will make or break the project; the critical risks must be identified. When a project or project task is completed in spite of a risk this is is called 'overcoming a risk." Overcoming a risk creates opportunity. On the other side of risk lies opportunity.
- Address risk by continuously looking for ways things can go wrong in "defining and scheduling work." Risk is primary to an organization and a project it is not separate from management. All projects equal risk without risk a project would not exist. "Risk is why you do business and plan projects"
- Focus on the high-risk and task that consume resources. Rank-order risks helps you to assess risk and keep the risk under a microscopic telescope.
- Monitor risks - Identify key risk milestones or points in project milestones where key decisions must be made. Milestones indicate if a equipment worked or didn't work, if a major resource was available, or a "key technology in new product worked as designed."
- Plan a response to risk will require an understanding of the project and impacts of different corrective actions. Create risk scenarios and schedule impacts. "Expected" scenario is the best guess at what actually will happen. "Pessimistic" scenario is the worst case and a "Optimistic " scenario is the best case.
Risk are identified from experience from past projects and careful assessment of current projects. Projects have many risks, however the important ones must be addressed. Importance would depend on the likelihood, impact and overall risk consequence. Likelihood is the probability a risk will occur which should be determined by experienced people. Risk impact would be the effect of the risk and how vital or the influence it may have on project schedule, cost or performance outcomes. Risk consequences would be a combination of both likelihood and impact. (View the two concepts as one) Risk consequence measures determine which risks should be addressed or ignored. As a rule, all risks with severe impact should be closely examined even when the likelihood of the occurrence is small.
Karen Callier
References:
(Barkley, 2004 p. 3).
(Nicholas, Steyn, 2008 p. 388).
(Barkley, 2004 p. 3).
(Nicholas, Steyn, 2008 p. 388).

